Variations and Site Request Form

What's the Project Address?

Readable Variation Number!


Choose ONE - the type of service required

Who is paying for the variation? External - Customer is paying; Internal - FSS is paying

Select the quote type

Select the Work type

Manual Handling Required for this variation?

How Long Vertical & How Long Horizontal for this variation?

Scaffolding Works Location for this variation?

Measurement and Configuration of Variation Scaffolding.

Scaffolding Works between walls?

Is Material available onsite?


Description Details
     Install scaffold with alloy stair access for Preschool-Admin block fire walls. See attached mark up. 5 board straight, 4 weeks hire, NO Engineering, 1 alloy stairs and Please provide LM (L) (H).  
     Install scaffold with alloy stair access for Admin block fire walls. See attached mark up. 5 board straight, 4 weeks hire, NO Engineering, 1 alloy stairs and Please provide LM (L) (H).  
     Install scaffold with alloy stair access for Main Switchboard Room Block Walls. See attached mark up. 5 board straight, 4 weeks hire, NO Engineering, 1 alloy stairs and Please provide LM (L) (H).  







Task Created!
Task Created By Reabie Pana
Job - FSS5762 - STRATHNAIRN ECEC - YEAR 6 SCHOOL Add Note 2025-04-04 10:46:16AM by Reabie Pana
Cost Added!
Variation Cost Added By Yousif Yousif
Job - FSS5762 - STRATHNAIRN ECEC - YEAR 6 SCHOOL Add Note 2025-04-04 03:28:55PM by Yousif Yousif
@Reabie Pana 437 m2 of scaffold 11Lm x12mH +27Lm x 5mH + 34 Lm + 5mH 293 m2 of mesh: Meash Area = 437 m2 (scaffold area) - 72 Lm (length of the scaffold) x2 = 437-144 = 293 m@ of mesh.
Job - FSS5762 - STRATHNAIRN ECEC - YEAR 6 SCHOOL Add Note 2025-04-04 03:35:20PM by Yousif Yousif
@Yousif Yousif See email sent 7/04 328PM for reference if attached mark up not visible
Job - FSS5762 - STRATHNAIRN ECEC - YEAR 6 SCHOOL Add Note 2025-04-07 03:44:12PM by Reabie Pana
Cost Added!
Variation Cost Added By Yousif Yousif
Job - FSS5762 - STRATHNAIRN ECEC - YEAR 6 SCHOOL Add Note 2025-04-08 01:11:30PM by Yousif Yousif
Cost Added!
Variation Cost Added By Yousif Yousif
Job - FSS5762 - STRATHNAIRN ECEC - YEAR 6 SCHOOL Add Note 2025-04-08 01:13:25PM by Yousif Yousif
Cost Added!
Variation Cost Added By Yousif Yousif
Job - FSS5762 - STRATHNAIRN ECEC - YEAR 6 SCHOOL Add Note 2025-04-08 01:31:20PM by Yousif Yousif
@Reabie Pana Area 1: 16.5 L x 6.5 H = 107.25 m2 of scaffold. The other 18 L (along grid A-E) were quoted in another variation. These 16.5 L are along grid A-02 and its return. Mesh = 16.5 L x 4 H = 50 m2 of mesh. Area 2: 11 L x 12 H +27 L x 5 H = 267 m2 11 L x 10 H + 27 m x 4 H = 218 m2 of mesh Area 3: 34 L x 5 mH = 170 m2 34 L x 4 mH = 136 m2
Job - FSS5762 - STRATHNAIRN ECEC - YEAR 6 SCHOOL Add Note 2025-04-08 02:08:05PM by Yousif Yousif
Email Send To Customer!
Send Email To Customer By Vinod Sharma
Job - FSS5762 - STRATHNAIRN ECEC - YEAR 6 SCHOOL Add Note 2025-04-10 03:12:39AM by Vinod Sharma
Email Send To Customer!
Send Email To Customer By Vinod Sharma
Job - FSS5762 - STRATHNAIRN ECEC - YEAR 6 SCHOOL Add Note 2025-04-10 03:18:22AM by Vinod Sharma
Email Send To Customer!
Send Email To Customer By Vinod Sharma
Job - FSS5762 - STRATHNAIRN ECEC - YEAR 6 SCHOOL Add Note 2025-04-10 03:20:29AM by Vinod Sharma
Cost Added!
Variation Cost Added By Yousif Yousif
Job - FSS5762 - STRATHNAIRN ECEC - YEAR 6 SCHOOL Add Note 2025-05-14 02:50:43PM by Yousif Yousif

Upload pictures of your request

Drag & drop files here, or browse

Preview
Image Preview

Who is submitting the form?