Job Name Stage Amount
Woden Bus Depot Closed Lost/Other AU$ 310300
Open Activities

Open Tasks 0
Open Meetings 0
Open Calls 0

Closed Activities

Closed Tasks 2
Closed Meetings 1
Closed Calls 1

FSS4567- RICHARD CROOKES (ACT) Jun 30, 2023
Randa Al-Rifai
Closed Time: 2023-06-30T08:51:28+05:30
Status: Completed
Estimating Task Type: Final Reprice - Priority 1


FSS4567- Richard Crookes Jul 05, 2023
Randa Al-Rifai
Closed Time: 2023-07-05T11:55:19+05:30
Status: Completed
Estimating Task Type: Final Reprice - Priority 1
Description: 1. ADD SCAFFSHILED AS AN OPTION COST FOR ALL TIES. NOTE: FINISH IS METAL CLADDING 2.FOR THE BUS SHELTER: ALLOY 1 X STRETCHER & 1 X ALLOY FROMGROUND TO ROOF AS AN OPTION COST 3..FOR THE WORKSHOP AREA: ALLOY 1 X STRETCHER & 1 X ALLOY FROMGROUND TO ROOF AS AN OPTION COST

New Meeting
Jul 04, 2023 05:30 AM - Jul 04, 2023 06:00 AM
Theo Bardis
Status: Meeting Successfully Completed
Description: discussed project and methodology. FSS and one other on this. Scaff to be required in about 4 weeks. update to scope require and quote to be re sent. to be awarded next week

Outgoing call to Ryan Partridge
Jul 11, 2023 07:17 AM
Theo Bardis
Contact Name:

Status: Completed
Descriptions: FSS around 80-90k more than Rovera. Going with them

Quotes

Action Job Name Subject Quote ref number Quote stage Quote Owner Cteated Time Grand Total GP%
Woden Bus Depot FSS4567.01 Q1580 Sent Randa Al-Rifai 2023-06-30T08:52:13+05:30 $310,300.00 45