Updated Successfully.
Update Contact
Contact Information
Description Information
Jobs

Job Name Stage Amount
NORTHEDGE SITE: BLOCK 01 SECTION 76, TAYLOR Closed Lost/Other AU$ 228500
Open Activities

Open Tasks 0
Open Meetings 0
Open Calls 0

Closed Activities

Closed Tasks 2
Closed Meetings 2
Closed Calls 1

FSS3264- NIKIAS DIAMOND (ACT) Feb 21, 2022
Saifan Butusian
Closed Time: 2022-02-22T07:21:00+05:30
Status: Completed
Estimating Task Type: Quote Secured Project - Priority 3
Description: NON EBA SPEAK TO ME ABOUT GP

FSS3264- NIKIAS DIAMOND Mar 22, 2022
Saifan Butusian
Closed Time: 2022-03-23T06:17:36+05:30
Status: Completed
Estimating Task Type: Final Reprice - Priority 1
Description: 1. since we are updating our costs for mesh and transport, see new costs that we discussed last week based on $220.00 PER LOAD TRANSPORT AND $20 PER ROLL SECOND HAND MESH BLOCK 1= 77,500 BLOCK 2= 43,000 BLOCK 3= 58,000 BLOCK 4= 49,0000 TOTAL JOB COST= $227,000 NOTE: THE WEEKS OF HIRE HAVE DECREASED AS PER MY EMAIL ON SUNDAY. THIS MAY BRING THE COSTS DOWN FURTHER RUN JOB AT 38% Also please answer if we can include in our price the clients request as per the email i sent on 20/3 to you

New Meeting
Mar 08, 2022 03:00 AM - Mar 08, 2022 04:30 AM
Theo Bardis
Status: Meeting Successfully Completed
Description: Went through the FSS quotation and SOW. Discussed allowances and how they pan to build in stages. Minor updates to be done in the way of weeks of hire, and adding a couple of option costs. FSS, Rovera, Alto, Waco and No Limit on this. Stated our price was a bit on the high side. updating it due to changes. Job to be awarded later this month. Will speak to the construction director who i know as well in the next week

New Meeting
Feb 16, 2022 03:00 AM - Feb 16, 2022 03:30 AM
Theo Bardis
Status: Meeting Successfully Completed
Description: Quotes due next week. Currently have Alto on the current job. Ben stated no issues with them. Discussed scope and they want us to capture everything we feel is required to deliver the job. Scaff not required until April. Will be making a decision in the next 2 weeks. Rovera, Alto, Waco quoting as well

Outgoing call to Callam Deeble
Apr 05, 2022 08:27 AM
Theo Bardis
Contact Name:

Status: Completed
Descriptions: Rovera was 50K lower than FSS.. FSS. ALTO & Waco all within 1-2 % of each other. Rovera basically bought the job

Quotes

Action Job Name Subject Quote ref number Quote stage Quote Owner Cteated Time Grand Total GP%
NORTHEDGE SITE: BLOCK 01 SECTION 76, TAYLOR FSS3264.01 Q1076 Draft Saifan Butusian 2022-02-22T07:29:20+05:30 $228,500.00 38

Campaigns